How the Loop Works

A plain account of what the Loop is, why tunnels cost so much, where the Vegas system stood in November 2026, and what the company and its critics say.

  • 68 milesTunnel approved by Clark County and the City of Las Vegas for the Vegas Loop, with 123 stations (company page, Nov. 26, 2026)Source [1]
  • 14 stationsVegas Loop stations the company lists as operating today (company page, Nov. 26, 2026)Source [1]
  • 1,355 per hourHighest passenger flow at the Convention Center Loop as of mid-July 2021 (TechCrunch)Source [2]
  • 4,400 per hourCapacity goal, reached in a May 2021 demonstration with three riders per vehicle (TechCrunch)Source [2]
  • 12 ftInternal tunnel diameter in TBC's Music City Loop FAQSource [3]

What the Loop is

The Loop is a point-to-point underground transit system built by The Boring Company (TBC). Passengers board a Tesla at a station, ride through a narrow tunnel, and exit at another station. TBC's Music City Loop FAQ describes a fleet of Teslas, "initially Model Ys and Model Xs," and tunnels with a 12 foot internal diameter [3]. Stations can be small, or larger with 20 vehicle stalls for sites such as airports or convention centers [3].

The design differs from a subway, which runs fixed trains on a schedule and stops at every station in sequence. The Loop sends individual vehicles carrying a few people directly between chosen stations. It also differs from a highway tunnel, which is sized for general traffic. Loop tunnels are single lane and closed to private cars. A ProPublica reporter who rode the system described traveling at 35 mph on "shoulderless roadways" [4].

TBC's Las Vegas page gives transit times of "between 2 and 8 minutes" [1]. Vehicles have human drivers. The company's Music City Loop FAQ says that system will also start with drivers and that autonomous vehicles may be explored in the future [3].

Hyperloop is a separate idea that is often confused with the Loop. In August 2013 Elon Musk published the Hyperloop Alpha paper, which proposed pods in a low-pressure tube between Los Angeles and San Francisco, with a cost estimate in the "$6 billion range" [5]. The Loop uses ordinary road vehicles in tunnels at near-road speeds and does not use a vacuum tube.

Why tunnels are expensive, and what TBC says it changes

Independent research points to several causes of high tunnel costs, and boring itself is only one. The NYU Marron Institute's Transit Costs Project found that Phase 1 of New York's Second Avenue Subway was "8 to 12 times more expensive than our composite baseline case" [6]. It said station construction methods "led station costs to triple through overbuilding" and that soft costs added 21 percent for that project [6]. It also reported that labor is 40 to 60 percent of hard costs [6]. Stations, labor, and soft costs all weigh heavily alongside the boring machine.

TBC's claimed changes target the tunneling step. Its Prufrock machine is designed to "install the tunnel liner simultaneously with mining," so it need not stop every 5 feet to place lining [7]. Prufrock arrives on a truck and "tilts down, and launches into the ground within 24 hours," which avoids a large launch pit [7]. The machines are remotely controlled from TBC's Bastrop Operations Center, and the company's stated speed target is 1 mile per week [7].

The other lever is size. TBC's Music City Loop FAQ lists a 12 foot internal diameter and a depth of about 30 feet [3]. A smaller bore moves less ground per mile. The FAQ adds that excavated material may be recycled or repurposed under applicable regulations [3].

The NYU findings suggest that cheaper boring alone would not close the cost gap for large public transit systems. A small single-lane system with simple stations avoids some of the cost drivers the report identifies [6], but it also carries far fewer people per tunnel.

Vegas Loop status (as of November 26, 2026)

The first system was the Las Vegas Convention Center (LVCC) Loop, which began carrying convention attendees in June 2021 [2]. The 2019 contract with the convention authority reportedly imposes a $300,000 penalty for each large convention where TBC cannot move about 4,000 people per hour [2].

Stations and routes, as of November 26, 2026: TBC's Vegas Loop page lists 14 stations and 28 expected by the end of the year [1]. It lists four routes as operational: the LVCC Loop (two tunnels, 9,030 ft), the Resorts World Connector (3,325 ft), the Westgate Connector (3,945 ft), and the Encore Connector (2,320 ft) [1]. Those four total about 3.5 miles. The page does not state a total of operating tunnel miles, and its list of active stations names 13 while its count says 14 [1]. Fox5 Las Vegas reported on September 14, 2026 that the company "currently operates 14 Loop stations," with stops at Virgin Hotels and near Paradise and Tropicana opening soon [8].

Approvals, as of the same date: the company page says "Clark County and the City of Las Vegas have approved 68 miles of tunnel and 123 stations" [1]. Approval is not construction. ProPublica reported in January 2025 that Boring had finished more than 5 miles of the planned 68 [4].

Airport connection: the Review-Journal reported on January 4, 2026 that TBC had begun limited Loop service to Harry Reid International Airport after the county's Department of Aviation approved a vehicle identification permit [9]. An airport spokeswoman said drop-offs were available at the departures curb and pick-ups would follow once transponders were installed [9]. The TBC page lists Airport T1 and T3 among its active stations [1]. As of September 14, 2026, Fox5 reported that the expansion would open in stages toward a connection to the airport and that the company had not released a completion date [8]. A dedicated tunnel to the airport has therefore not been confirmed as open.

Ridership: the company says the system has "transported more than 4 million passengers" [1]. That is a company claim. ProPublica reported that the Regional Transportation Commission said it could not check Boring's ridership claims because the system is private [4]. Between early June and mid-July 2021, TechCrunch reported, an average of two passengers rode in each LVCC Loop vehicle [2].

Capacity is where claims and measurements diverge most. TechCrunch reported that TBC reached its 4,400 passengers per hour goal in a May 2021 demonstration by packing three riders into each of 62 vehicles, while the highest flow during actual operations by mid-July 2021 was 1,355 [2]. The LVCC does not usually host its largest conferences in summer, so a low peak in July does not by itself show a design limit [2]. For comparison, ProPublica quoted the convention authority's chief as saying the monorail carries 3,400 passengers per hour and the regional bus system 7,500 [4].

Criticisms and open questions

Capacity is the most common technical criticism. A vehicle that carries a few people cannot match the throughput of a train, and the measured LVCC peak of 1,355 passengers per hour was far below the 4,400 goal [2]. Supporters respond that tunnels and stations can be added in parallel and that point-to-point service avoids intermediate stops. Testing that claim depends on ridership data that outsiders cannot yet check [4].

On safety and egress, TBC says its system will "meet or exceed" the NFPA-130 fire and life safety standard [3]. Critics question how evacuation works in a narrow single-lane tunnel. ProPublica reported that Fortune counted at least 67 tunnel breaches since 2022, including outside vehicles, a skateboarder, and a pedestrian [4].

Worker safety has drawn documented enforcement. ProPublica reported that Nevada OSHA fined the company more than $112,000 in 2023 and that Boring contested the violations [4]. Fortune reported that on May 28, 2025 Nevada OSHA issued three willful citations with proposed penalties of $425,595 after a December 2024 fire drill in which two firefighters reported leg irritation, and that the citations were withdrawn after a state legal review found the key elements for a citation were not met [10]. Boring's lawyer argued that the key breakdowns were "committed by CCFD employees, not TBC employees." The fire department disputes this [10].

Environmental enforcement has also been reported. Fortune reported in November 2025 that the Clark County Water Reclamation District was issuing $493,297.08 in fines over drilling fluid dumped into the sewer system [11]. A letter from Boring's legal affairs director acknowledged that "water was improperly discharged to the sewer system" [11]. Separately, the Nevada Independent reported that state regulators accused the company of nearly 800 violations over two years, including 689 missed inspections and nearly 100 alleged new violations of a 2022 settlement [12]. The state reduced the penalty to $242,800 from a possible $3 million or more, and the company was disputing the letter [12].

Oversight is the last open question. ProPublica reported that Clark County removed Boring's amusement and transportation system permit in May 2024, a permit that had required injury reporting and gave the county inspection authority [4]. Because the system is privately operated and receives no federal funding, ridership, cost per mile, and safety data are largely self-reported, which limits independent evaluation [4].