Public Policy, Permitting and Approvals
Tunnels in the US are approved by a patchwork of federal, state and local processes. Where a project touches federal money or land, NEPA applies. Where it does not, local franchise and land use decisions carry most of the weight.
- 104 stations, 68 milesVegas Loop plan the convention authority urged the county and city to approve, per ProPublica (January 2025). The company now cites 123 approved stationsSource [1]
- 50 yearsTerm of the Clark County franchise agreement approved in October 2021Source [2]
- More than $112,000Nevada OSHA fine reported for 2023, which the company contestedSource [1]
- 1.14 milesLength of the Hawthorne, California test tunnel, built for less than $10 million per the companySource [3]
How a tunnel gets approved in the US
There is no single permit for a tunnel. Approval is a stack of decisions, and which layers apply depends on who owns the land, who pays, and which agencies must sign off. The central federal law is the National Environmental Policy Act (NEPA). It requires federal agencies to examine the environmental effects of proposed actions and weigh alternatives before deciding. It is triggered by what EPA calls "major federal actions significantly affecting the environment," which include permit decisions, federal land management actions and construction of publicly owned facilities [4].
NEPA has three tiers of review. An action that "normally does not have a significant effect on the human environment" can be handled with a categorical exclusion. Otherwise the agency prepares an environmental assessment (EA) to decide whether significant effects are likely. If they are, an environmental impact statement (EIS) follows, and EPA says its requirements are "more detailed and rigorous" than those for an EA [5].
The practical consequence is that a privately funded tunnel on private or local public land can avoid NEPA altogether. A tunnel that needs a federal permit, crosses federal land or uses federal highway rights of way generally cannot. The proposed DC to Baltimore Loop is an example. In April 2019 the US Department of Transportation released a draft EA for it and called that an "early milestone" in the permitting process [6].
States can add their own layer. California's Environmental Quality Act (CEQA) applies to state and local agencies, regardless of federal involvement. The California Attorney General describes it as requiring that "state and local agencies disclose and evaluate the significant environmental impacts" of projects [7]. A city can decide a project is exempt, but residents can sue over it. In the Los Angeles case below, NBC reported a suit over a plan to "exempt the project from environmental review requirements," though NBC does not name the statute [8].
Beyond environmental review, a tunnel typically also needs local land use approval, a franchise or right of way agreement to occupy public property, building and grading permits for each station and shaft, protection of existing utilities, and fire and life safety review. Those layers vary by jurisdiction.
Las Vegas: local approval, private funding
Las Vegas is the one place where Loop tunnels have been built at scale, and it happened largely through local decisions. ProPublica reports the project is privately operated and receives no federal funding [1]. The Las Vegas Convention and Visitors Authority (LVCVA) contracted for the Convention Center Loop, which opened in 2021. According to ProPublica, the authority committed $52.5 million in bonds for it and has paid the company about $4.5 million a year to operate it [1]. The authority's board approved a $48.6 million contract in 2019 [23]. No public report found gives a final contract value, and the funding page explains the gap between the contract and the bond amount.
On October 20, 2021, the Clark County Commission unanimously approved a special use permit and a franchise agreement. County reporting says the permit lets the company apply for building permits, while the franchise lets it operate the system, collect fares and oversee advertising and partnerships [9]. TechCrunch reported the franchise runs 50 years and covered a route growing from 1.7 miles to 29 miles with 51 stations. It also reported that the company would pay for the tunnels and that a separate franchise from the City of Las Vegas was still needed [2].
The city approval followed in June 2022. Construction Dive reported that the Las Vegas City Council voted unanimously for a "50-year, non-exclusive agreement" letting the company build and operate tunnels in city right of way [10]. That vote covered five stations beneath downtown, and the company still had to win approval of design studies such as fire and safety, geological and drainage reports [10].
The scope grew afterward. ProPublica reports that the county approved "a roughly 25-mile expansion and 18 new stations" at a 2023 zoning meeting, and that the City Council approved a 2023 extension as well [1]. The convention authority urged approval of plans for 104 stations across 68 miles of tunnels [1]. Station counts depend on the date. ProPublica's 104 is from January 2025, and in November 2026 the company's Vegas Loop page listed 68 miles and 123 stations as approved [22].
- 2019: ProPublica reports that groundwater discharged without a permit led to a state settlement and a $90,000 fine [1]. The Nevada Independent says the settlement agreement was signed by a Boring executive in 2022 [24].
- 2021: Nevada officials sent a letter warning against actions that could cause unpermitted discharge of groundwater [1].
- 2023: Nevada OSHA fined the company more than $112,000. ProPublica says the company disputed the allegations and contested the violations [1].
- 2023: The county approved two tunneling permits retroactively, adding a $900 fee to each [1].
- ProPublica's central critique is oversight, not legality. It reports that Boring did not respond to repeated requests for comment, though company records show a manager writing that "we take this very seriously" [1].
Fort Lauderdale and Florida
Fort Lauderdale was the most prominent Florida proposal, a pair of tunnels linking downtown to the beach along Las Olas Boulevard. In March 2021 Mayor Dean Trantalis said "Our city commission is unanimously in favor of this." He added that county and metropolitan planning organization participation would be needed to help with funding [11].
Momentum faded. The Sun-Sentinel reported on January 30, 2025 that the idea was suspended but could be revisited at any time [12]. A previous commission opposed moving ahead by a 3 to 2 vote and delayed paying the company $375,000 for a feasibility study. The city had spent $50,000 on the proposal, and the tunnels were estimated at $100 million [12]. The mayor said the city would first need to see "if they're still interested in fully funding the project" as originally proposed [12].
Canceled or stalled projects, and the pattern
Chicago O'Hare Express. Mayor Rahm Emanuel selected the company in 2018 for an 18-mile route from Block 37 to O'Hare, with Musk promising to cover the roughly $1 billion cost. In June 2019 his successor Lori Lightfoot doubted it could be built without public money and questioned the bidding process. Her office said she was "evaluating several major transit projects" [13]. By September 2019 a WBBM report relaying Crain's Chicago Business commentary called the idea "effectively dead" [14]. The project was never built.
Los Angeles Westside test tunnel. The company proposed a test tunnel under Sepulveda Boulevard, and the city moved to exempt it from environmental review. Resident groups sued. On November 27, 2018 the parties announced a settlement, and the company said it "no longer seeks the development of the Sepulveda test tunnel" [15]. NBC News reported the groups had sued over a plan to "exempt the project from environmental review requirements" [8].
Dugout Loop. The proposed 3.6-mile tunnel to Dodger Stadium was announced in 2018. In April 2021 Ballpark Digest reported that the project had not reached groundbreaking, a year after city officials described it as in environmental review [16]. No formal withdrawal has been reported, so the project is best described as stalled.
DC to Baltimore Loop. The draft EA released April 17, 2019 covered two parallel 35-mile tunnels paid for by the company [6]. A draft is an early step, not an approval, and no final federal decision has been reported.
Hawthorne test tunnel. This one was built. The company lists the 1.14-mile tunnel as "Complete and Operational," finished in December 2018 for less than $10 million, according to the company's own page as of November 26, 2026 [3].
No single cause explains the pattern. Chicago depended on one political champion who then left. Los Angeles ended in a settlement after residents sued over an exemption from environmental review. Dodger Stadium and Fort Lauderdale stalled once review, funding questions or local doubts arrived. Las Vegas advanced where a single local client wanted it, the county was willing to grant a franchise, and no federal review was triggered. Supporters would say that shows local flexibility. Critics would say the approvals that worked were the ones with the least independent scrutiny [1].
Nashville: the Music City Loop
The Music City Loop, announced in 2025, would run from Nashville International Airport to downtown and is described as 100 percent privately funded. In July 2025 a Tennessee executive subcommittee unanimously approved a lease for the company to start work on a state-owned lot below the Capitol. Gov. Bill Lee said the project "will be a great one" [17].
The company reports that the Tennessee Department of Transportation tunnel permit and lease agreement was executed on February 25, 2026, covering 25 miles of tunnel within state right of way. It says the project needs 45 permits and approvals in all, that "All 37 permits and approvals required ahead of tunneling have been obtained," and that the other 8 relate to additional launch sites. The Metropolitan Nashville Airport Authority approved an airport station by an 8 to 0 vote [18]. These figures come from the company's own June 2026 update.
Not everyone is satisfied. The pastor of First Baptist Church Capitol Hill, next to a construction site, has raised concerns about ground impacts and said "I sent a letter to the governor that still hasn't been acknowledged or responded to" [19].
Federal policy context
Two recent changes bear on NEPA. First, the Fiscal Responsibility Act of 2023 (the debt ceiling law) amended the statute. An EIS "shall not exceed 150 pages, not including any citations or appendices," with a 300 page cap for those of extraordinary complexity, and an EA is capped at 75 pages [20]. The law also sets deadlines of 2 years for an EIS and 1 year for an EA, measured from the earliest trigger such as a notice of intent. A lead agency may extend a deadline by the time needed, and a project sponsor can petition a court if a deadline is missed [20].
Second, on May 29, 2025 the Supreme Court decided Seven County Infrastructure Coalition v. Eagle County, reversing the D.C. Circuit. Justice Kavanaugh wrote for five justices, three more concurred in the judgment, and Justice Gorsuch did not participate [21]. The Court held that an EIS need not address the effects of separate projects, and wrote that "courts should afford substantial deference to the agency as to the scope and contents of the EIS" [21]. It also said a deficient EIS does not necessarily require vacating a project approval [21].
The effect on tunnels is not yet settled. Tunnels that need a federal permit might see faster, narrower and harder to challenge reviews. Tunnels approved entirely locally are not touched by NEPA, and state law such as CEQA is unaffected by a federal ruling. Supporters of the changes argue that long reviews delay infrastructure for little benefit. Critics argue that narrower review reduces public scrutiny.
Watch
Picked for this page. The full list is on Videos.
-
Clark County approves 'Vegas Loop' resort corridor agreement with Boring Co.
KTNV Channel 13 Las Vegas · 2021 · 2:39
KTNV report from October 2021 on Clark County approving the Vegas Loop resort corridor agreement with TBC. News coverage of a key local approval, not the hearing itself.
-
Las Vegas workers crushed, ejected: Lawmakers review Boring Co. projects
8 News Now Las Vegas · 2026 · 2:21
Local news report from 2026 on Nevada lawmakers reviewing allegations of worker injuries and other incidents on Boring Company projects. Relevant to oversight and workplace safety.
-
Nevada OSHA finds multiple safety violations at Elon Musk's Boring Company tunnel worksite
News 3 Las Vegas · 2024 · 2:57
News 3 Las Vegas report from February 2024 on Nevada OSHA finding multiple safety violations at a TBC tunnel worksite. Shows regulatory scrutiny at one point in time.
-
Commission Wrap Up October 5, 2021
City of Fort Lauderdale · 2021 · 4:46
Official City of Fort Lauderdale recap of the October 5, 2021 commission meeting, in which Mayor Dean Trantalis discusses the Boring Company tunnel proposal. Short, and the city's own framing.
-
Fort Lauderdale commissioners to hold first vote for Elon Musk's traffic tunnel proposal
WPLG Local 10 · 2021 · 2:04
WPLG report on Fort Lauderdale commissioners preparing a first vote on the tunnel proposal in October 2021. Pairs with the city's own recap of the same meeting.
-
Musk’s Boring Tunnel in Nashville Faces Backlash
Bloomberg News · 2026 · 1:02
Brief Bloomberg News piece from February 2026 on criticism of TBC's Nashville tunnel plan. A counterpoint to the launch announcement, with little detail at this length.
-
Elon Musk's Boring Company To Build Express Tunnel To O'Hare
CBS Chicago · 2018 · 2:23
CBS Chicago report from June 2018 on the city negotiating with TBC over an express tunnel to O'Hare. Context on a project that was never built.
-
How Feasible Is Elon Musk's Proposed 'Dugout Loop' To Dodger Stadium? The Experts Weigh In
CBS LA · 2018 · 1:48
CBS LA asks experts in 2018 about the proposed Dugout Loop to Dodger Stadium, including faults and groundwater. Context on a project that was never built.
Further reading
- National Environmental Policy Act review process, US Environmental Protection Agency (article). Plain explanation of categorical exclusions, EAs and EISs.
- Elon Musk's Boring Company is tunneling beneath Las Vegas with little oversight, ProPublica (article). Detailed critical reporting on Nevada approvals and enforcement.
- Seven County Infrastructure Coalition v. Eagle County, No. 23-975, Supreme Court of the United States (primary). Opinion of the Court, May 29, 2025.
Sources
- ProPublica, Elon Musk's Boring Company is tunneling beneath Las Vegas with little oversight
- TechCrunch, Elon Musk's Boring Company gets initial OK to expand Loop under Las Vegas Strip (Oct 20, 2021)
- The Boring Company, Research and Development Tunnel
- US EPA, What is the National Environmental Policy Act?
- US EPA, National Environmental Policy Act Review Process
- FreightWaves, Musk's DC-Baltimore loop tunnel clears regulatory hurdle (Apr 19, 2019)
- California Attorney General, California Environmental Quality Act (CEQA)
- NBC News, Elon Musk's L.A. freeway tunnel won't see the light of day (Nov 27, 2018)
- KTNV Las Vegas, Clark County approves Vegas Loop resort corridor agreement with Boring Co.
- Construction Dive, Las Vegas approves Boring Co. loop under downtown (Jun 22, 2022)
- CBS Miami, Boring Company, Fort Lauderdale closer to making tunnel project a reality (Mar 5, 2021)
- Sun-Sentinel via Yahoo News, Fort Lauderdale mayor says he's still open to building twin tunnels to the beach (Jan 30, 2025)
- CBS Chicago, Elon Musk O'Hare express tunnel (Jun 4, 2019)
- WBBM Newsradio, High speed tube loop to O'Hare looks dead (Sep 26, 2019)
- ABC7 Los Angeles, The Boring Company shelves Sepulveda test tunnel after reaching settlement in lawsuit (Nov 28, 2018)
- Ballpark Digest, Musk's Boring to Dodger Stadium dead (Apr 16, 2021)
- WSMV, Lease for The Boring Company approved for new Music City Loop while questions loom (Jul 31, 2025)
- The Boring Company, Music City Loop blog post (Jun 1, 2026)
- NewsChannel 5 Nashville, Gov. Bill Lee clears way for Music City Loop, downtown church raises concerns
- US Congress, Fiscal Responsibility Act of 2023, Public Law 118-5
- Supreme Court of the United States, Seven County Infrastructure Coalition v. Eagle County, No. 23-975 (May 29, 2025)
- The Boring Company, Vegas Loop project page
- CNBC, Boring Co. lands first paying customer, a $48.6 million contract in Las Vegas (May 23, 2019)
- The Nevada Independent, Elon Musk's Boring Co. accused of nearly 800 environmental violations
Last reviewed November 26, 2026. Spot an error? Use Contact in the header.